Crack filling schedule from March 14 on

HERON’S FOREST CRACK FILLING ROAD SCHEDULE

(note this is done the day before your road section is sealed)

ROAD WILL NOT BE CLOSED

BUT, NO PARKING ON ROAD THAT CRACK FILLING IS SCHEDULED!!!

ABSOLUTELY NO WATER ON THE ROAD 2 DAYS BEFORE CRACK FILLING!!

 MARCH 14th Both lanes of Grallatorial and North bound lane of Rookery from Grallatorial to Gulf Beach (exit of Heron’s Forest).

 MARCH 15th Both lanes of Rookery from Foggy Bottom going North to Bittern. West bound lane of Jabiru from Rookery to Limpkin. West bound lane of Rail from 9860 Rail to Rookery.

 MARCH 17th Both lanes of Rookery from Tanager to Foggy Bottom. East bound lane of Jabiru from Limpkin to Rookery. East bound lane of Rail from Rookery to 9945 Rail.

 MARCH 18st All of the Loop on the East end of Rail Circle and both cul-de-sacs on the loop of Rail Circle. South Bound lane of Rookery from Gulf Beach to Jabiru (entrance of Heron’s Forest).

 MARCH 21nd Pool parking lot. South bound lane of Rookery from Jabiru to Bittern. North bound lane of Rookery from Rail to Grallatorial.

 March 22- CRACK FILLING (RESCHEDULE OF MARCH 1 BECAUSE OF RAIN)   Both lanes of Lorikeet.

 MARCH 24-CRACK FILLING (RESCHEDULE OF MARCH 10TH BECAUSE OF RAIN) 10100-10108 Bittern and Grackle Court. 

 CRACK FILLING CAN NOT BE DONE IF ROAD OR CRACKS ARE WET. RESIDENTS CAN NOT PARK ON THEIR ROAD ON DAY CRACK FILLING IS SCHEDULED!!!

If any questions contact Perdido Sand Realty, 850-492-2000.

 